LiveERCOT large-load review
On 3 August 2026 Governor Greg Abbott directed the Public Utility Commission of Texas and ERCOT to verify and audit large-load requests.
Wind turbines at the Roscoe Wind Farm in West Texas. Photo: Matthew T Rader, CC BY-SA 4.0.
Why it matters
Texas is where data-centre demand meets an energy-only market. How ERCOT verifies and sequences large-load requests decides how fast new load connects and who pays for the grid that serves it.
Key numbers
- 66.4 GWBatch Zero base classification
- 127.9 GWLarge load studied in Batch Zero
Figures as quoted in our articles on this event.
Key developments
ERCOT issues Batch Zero conditional classifications, with verification due in December. Read our analysis
Governor Abbott directs the PUCT and ERCOT to verify and audit large-load requests. Read our analysis
Our coverage 12 articles
Analysis · United States · Powering the AI Transition · US LNG investment decisions
Texas Gas Has Two Big New Customers: LNG Trains and Data CentersAnalysis · United States
Soft September LMPs, Hard Large-Load QueuesAnalysis · United States · Powering the AI Transition
Texas Puts a Price on a Place in ERCOT's Queue, Then Freezes Data Center PermitsAnalysis · United States
ERCOT Pauses Batch Zero Study and Large Data-Centre Energisation after Abbott DirectiveAnalysis · United States · Powering the AI Transition
ERCOT Sets an All-Time Peak of 91,134 MW, Beating the 2023 Record by About 6%Analysis · United States · Powering the AI Transition
Texas Writes the First Rulebook for Giant Loads: What SB 6 Asks of Data CentersAnalysis · United States
ERCOT Load Growth, Data Centres and the Texas Reliability Problem SetAnalysis · United States · Powering the AI Transition
ERCOT's 218 GW Forecast Is Mostly Data Centers on Paper, So It Wrote a Discount